Completed Contract
| Nagmati Dam: DPR | |
|---|---|
| Contract ID | ICB/BRBIP/PIIU-01-s |
| Project Name | Nagmati Dam: DPR |
| Work Name | Detailed Feasibility Study of Nagmati Dam |
| Contract Name and address | Entura associated with Sub-Consultant TMS |
| Date of agreement | Nov. 6, 2015 |
| Date of completion as agreement | Sept. 6, 2017 |
| Date of completion (Revised) | |
| Amount of Agreement | 258420885.16 |
| Actual Expenditure | 216193714.67 |
| Current Project Status | Completed |
| Contractor Libility Status | Completed |
| Major works completed | Investigation and Update of Feasibility study, Detailed Engineering Design and Preparation of Bid Document |