Progress Contract
S.N | Name of work | Contract ID | Name of Contractor | Contract Amount Rs | Date of Agreement | Date of completion as per Agreement | Revised Date of Completion | Time Extended based on Original schedule | Time Elapsed based on revised schedule % | Time Remaining based on extended schedule(Days) | Financial Progress Rs | Physical Progress | Progress Status | Remarks | |||
Amount | Percent | Last Payment Date | Percent | Date | |||||||||||||
1 | Design and Build of Dhap Dam, Access Road and Environmental Protection Works | ICB/BRBIP/PIIU-01-W | Guangzhou-Lama-Raman JV | 510752348.00 | Sept. 10, 2015 | Oct. 8, 2017 | Oct. 15, 2022 | 341.50 | 133.91 | -879 | 478531278.00 | 94% | March 9, 2022 | 99.00 | Nov. 10, 2022 | Laging behind | Expenditure excludes PA and includes VAT, Comparable to Agreement Amount. Total expenditure is 50,95,54,553 |