Ongoing Contract
| Dhap Dam: Main Dam | |
|---|---|
| Contract ID | ICB/BRBIP/PIIU-01-W |
| Project Name | Dhap Dam: Main Dam |
| Work Name | Design and Build of Dhap Dam, Access Road and Environmental Protection Works |
| Contract Name and address | Guangzhou-Lama-Raman JV |
| Date of agreement | Sept. 10, 2015 |
| Date of completion as agreement | Oct. 8, 2017 |
| Date of completion (Revised) | Oct. 15, 2022 |
| Amount of Agreement | 510752348.00 |
| Actual Expenditure | 478531278.00 |
| Current Contract status | Ongoing |
| Contractor libility status | Ongoing |
| Major works completed | Completed Works: Main Dam Body, Spillway, Outlet, Saddle Dams, Remaining: Instrumentation |